ESB New HQ

Project Name

ESB New HQ

Client:

ESB Ireland

Sector:

Private

Location:

Fitzwilliam Street Dublin

Main Contractor:

PJ Hegarty

Contract Period:

Dec 2017 - June 2021

  • New ESB Headquarters.
  • Two Storey Basement dig 8.00m deep, approx 72,000m3 excavation brownfield site.
  • M&N achieved on average over 100 artic loads per day during bulk dig.
  • Rock breaking 24,000m3 & disposed off site.
  • Complex dig due to obstructions in ground reinforced concrete which had to be broken out from existing building.
  • Disposal 60,000 tonnes contaminated material off site for export to barges and licensed tips in Ireland.
  • Disposal concrete rubble to recycling facility.
  • Substructure works – blinding, breaking piles, sub slab drainage.
  • Works within existing Georgian building including ducting, connections, drainage, breaking piles.