Charlemont Square

Project Name

Charlemont Square

Client:

McGarrell Reilly Group

Sector:

Private

Location:

Charlemont Street Dublin2

Main Contractor:

JJ Rhatigan

Contract Period:

Jan 18 - Nov 19

  • A mixed used development double storey basement dig 8.00m deep brownfield site.
  • M&N excavated approx 130,000m3 material and disposed off site.
  • Temporary works – M&N installed propping to perimeter basement.
  • M&N achieved over 130 artic loads per day at height project.
  • Substructure – Blinding works carried out.
  • Sub slab drainage & In slab drainage works.