Data Centre Phase 1 DB4
Project Name
Data Centre Phase 1 DB4
Client:
Blue Chip Company
Sector:
Private
Location:
West Dublin
Main Contractor:
John Sisk & Sons
Contract Period:
Nov 2011- Sept 2012
- New Extension to Existing Data Facility 8000m2
- Reduce level strip and disposal 6,000m3 Greenfield Inert to licensed Tip. Site Prep & Bulk Filling Hardcore.
- Substructure pad foundations & bulk filling lean mix.
- Internal Grading Floors & Perimeter Ground Beams. Internal Drainage &Pop Ups/ Radon system.
- Storm/Foul Drainage. Deep Petrol Interceptors.
- Temporary Works.
- Ducting LV/COMMS/MV Power supply.
- Watermain/Sprinkler Mains.
- Connections to local authority services.
- Working in Live data centre around existing live services.
- External Works – Footpaths, Roads, Kerbs, Paving, Generator Compounds, Yard Slabs.
- Landscaping – Construction Berms & Topsoil external areas.