ESB New HQ
Project Name
ESB New HQ
Client:
ESB Ireland
Sector:
Private
Location:
Fitzwilliam Street Dublin
Main Contractor:
PJ Hegarty
Contract Period:
Dec 2017 - June 2021
- New ESB Headquarters.
- Two Storey Basement dig 8.00m deep, approx 72,000m3 excavation brownfield site.
- M&N achieved on average over 100 artic loads per day during bulk dig.
- Rock breaking 24,000m3 & disposed off site.
- Complex dig due to obstructions in ground reinforced concrete which had to be broken out from existing building.
- Disposal 60,000 tonnes contaminated material off site for export to barges and licensed tips in Ireland.
- Disposal concrete rubble to recycling facility.
- Substructure works – blinding, breaking piles, sub slab drainage.
- Works within existing Georgian building including ducting, connections, drainage, breaking piles.