Fibonacci Square
Project Name
Fibonacci Square
Client:
Ronan Group Real Estate
Sector:
Private
Location:
Ballsbridge
Main Contractor:
John Sisk & Sons
Contract Period:
April 2019 To February 2022
- Facebook New International Headquarters.
- Two storey basement dig within secant piled wall 15.00m deep.
- Approx 135,000m3 excavated & disposed off site brownfield site within 28 week programme duration.
- M&N achieved on average 130 artic loads per day at height of project in busy City Centre environment.
- M&N disposed circa 30,000 tonnes contaminated material for export to barges and licensed facilities in Ireland.
- M&N logistical operations enabled smooth truck movements daily on site.
- M&N provided two full time Road Sweepers daily.
- 25,000m3 Rock Breaking.
- Substructure works Blinding, Groundbeams & formwork, backfilling sub-basement walls.
- Under slab & In slab drainage.
- Associated Site Services & Connections.